1. Issue: Project Planning
Activities: 1) Deploy DMS 1.0 to WGRFC on October
30, 2003 2) DMS Training at WGRFC November 12 - 14
Actions required by OHD/HL management: none
2. Issue: Project Execution
Activities: 1) Testing at ABRFC
Actions required by OHD/HL management: none
3. Issue: Upcoming Work
Activities: 1) Testing DMS 1.0 at WGRFC 2) Prepare
for DMS training at WGRFC
Actions required by OHD/HL management: none
4. Issue: Tracking Hours
Activities: To verify the time estimates in the
project schedule, we will be
tracking the number of hours spent on the project. I need ABRFC,
Apex, and each
person in OHD to let me know the number of hours worked for the
previous week(s).
Actions required by OHD/HL management: none