The
topics covered are:
1. Project Planning
2. Project Execution
3. Upcoming Work
4. Tracking Hours
1.
Issue: Project Planning
Activities: 1) DMS Training at WGRFC November 12
- 14
Actions required by OHD/HL management: none
2. Issue:
Project Execution
Activities: 1) Testing at ABRFC 2) Installation
at WGRFC
Actions required by OHD/HL management: none
3. Issue:
Upcoming Work
Activities: 1) Testing at WGRFC 2) Continue testing
at ABRFC 3) Prepare for DMS training at WGRFC
Actions required by OHD/HL management: none
4. Issue:
Tracking Hours
Activities: To verify the time estimates in the
project schedule, we will be
tracking the number of hours spent on the project. I need ABRFC,
WGRFC, and
each person in OHD to let me know the number of hours worked for
the previous
week(s).
Actions required by OHD/HL management: none |