Project Status 11/21/2003
The topics covered are:
1. Project Planning
2. Project Execution
3. Upcoming Work
1. Issue:
Project Planning
Activities:
1) Based on feedback from WGRFC and Diane Cooper from ABRFC we'll
be
making another release of DMS 1.0 to incorporate some minor fixes
in about the 2
- 4 week time frame.
Actions required by OHD/HL management: none
2. Issue:
Project Execution
Activities:
1) We conducted 3 days of training at WGRFC on 11/12 - 11/14
2) WGRFC staff was appreciative of the training and seemed enthusiastic
working
with it
3) We have prioritized ABRFC and WGRFC's request and identified
which are most
important
Actions required by OHD/HL management: none
3. Issue:
Upcoming Work
Activities:
1) Work on prioritized fixes to DMS 1.0 2) Provide support to WGRFC
and ABRFC during testing
Actions required by OHD/HL management: none
|