Issue: Project Planning
Activities: Seann and I met with OHD/HL management
on 5/7/2003 to go over the updated project schedule. We were
given the ok to proceed. The current project schedule is divided
into 2 separate ones, one for DMS 1.0 (enhancing the prototype)
and another for DMS 2.0 (future AWIPS version of the distributed
modeling system). After we make some minor adjustments to
the schedule, we plan to make it accessible over the web.
We will also have a draft project plan, a textual description of
the project schedule, to present OHD/HL management in two weeks.
Actions required by OHD/HL: Attend
a meeting in 2 weeks to review the project plan and schedule
Issue: Project Execution
Activities: APEX has purchased and is using
the Portland Group Fortran 90 compiler with the existing HL-RMS
code. APEX is documenting their findings about the existing prototype
and any proposed enhancements. We have been in touch with ABRFC
and after talking with them we have a good feel for what the prototype
should include. We will be in touch with them again early
next week to confirm our earlier conversations on the functionality
to include in the prototype.
Actions required by OHD/HL: none