The topics covered are:
1. Project Planning
2. Project Execution
3. Upcoming Work
4. Tracking Hours
1. Issue: Project Planning
Activities: The result from our requirements document
review this morning is that you have given us approval to proceed
with the "Essential" scope level of requirements. You
will give us information about specific resources we need from OHD
in the next couple of weeks. Also, besides these weekly emails,
the only other meetings scheduled with OHD/HL management until early
September are some design reviews with HSEB leadership early next
month.
Actions required by OHD/HL management: Let me know
of specific resource needs I identified at the meeting
2. Issue: Project Execution
Activities: 1) OHD, ABRFC and Apex finalized the
document describing the requirements for all phases of DMS 1.0 2)
Seann and I met with the rest of HSMB to go over the proposed requirements
for DMS 1.0. One issue raised was. HSMB wants to make sure there
is a procedure in place for making enhancements to XNAV for the
period between DMS 1.0 and DMS 2.0. We have started to think about
this. One thing we plan to do to help, is CM all the code (XNAV
and HL-RMS) here at OHD.
Actions required by OHD/HL management: none
3. Issue: Upcoming Work
Activities: 1) APEX will begin looking at design
specifics for the issues related to HL-RMS performance. 2) We will
work with ABRFC to start the design process of the enhancements
to XNAV
Actions required by OHD/HL management: none
4. Issue: Tracking Hours
Activities: In order to verify the time estimates
in the project schedule, we have set up a way to track the number
of hours spent on the project. I need ABRFC, Apex, and each person
in OHD to let me know the number of hours worked for the previous
week(s).
Actions required by OHD/HL management: none