The topics covered are:
1. Project Planning
2. Project Execution
3. Upcoming Work
4. Tracking Hours

1. Issue: Project Planning
Activities: Set up a teleconference for early next week to introduce WGRFC to the DMS project
Actions required by OHD/HL management: none

2. Issue: Project Execution
Activities: 1) ABRFC presented their design for enhancements to XNAV to Jon Roe during a teleconference on 7/16. ABRFC raised some questions regarding running DMS in a AWIPS vs NON-AWIPS Linux environment. We agreed to get back to them. 2) Xiao Biao and Wen have each selected two of the four requirements HSEB is responsible for. They then met with Frank Rusch to discuss his design of HL-RMS enhancements.
Actions required by OHD/HL management: Answer ABRFC questions about what environment to use for testing DMS

3. Issue: Upcoming Work
Activities: 1) All development groups (Apex, OHD, and ABRFC) will continue building
Actions required by OHD/HL management: none

4. Issue: Tracking Hours
Activities: In order to verify the time estimates in the project schedule, we have set up a way to track the number of hours spent on the project. I need ABRFC, Apex, and each person in OHD to let me know the number of hours worked for the previous week(s).
Actions required by OHD/HL management: none

 