The topics
covered are:
1. Project Planning
2. Project Execution
3. Upcoming Work
4. Tracking Hours
1. Issue:
Project Planning
Activities: We scheduled a conference call with
ABRFC and WGRFC on Tuesday August 19th at 10 am to discuss ABRFC's
progress on enhancements to XNAV and the DMS environment at each
RFC.
Actions required by OHD/HL management: none
2. Issue:
Project Execution
Activities: All groups worked on their parts of
the development
Actions required by OHD/HL management: none
3. Issue: Upcoming Work
Activities: All development groups (Apex, OHD,
and ABRFC) will continue working to meet the September 3, 2003 due
date for new development
Actions required by OHD/HL management: none
4. Issue:
Tracking Hours
Activities: To verify the time estimates in the
project schedule, we have set up a spreadsheet to track the number
of hours spent on the project. I need ABRFC, Apex, and each person
in OHD to let me know the number of hours worked for the previous
week(s).
Actions required by OHD/HL management: none
|